What should be scoped before the external auditor arrives?

What the audit must verify, over what scope, against what criteria, and with what guarantee of independence. Scoping is written down, and it is validated by your audit programme manager, the audit client in the sense of ISO 19011:2026, not by the auditor.

Element

Question to settle

Written evidence

Objective

Scheduled audit, pre-transition audit, audit after an incident or complaint?

Annual programme, audit request

Scope

Which processes, lines, teams, sites, off-site storage?

Audit plan

Criteria

Which standards and clauses, internal procedures, customer specifications, legal texts?

Audit plan, checklist

Dates

When is the audited activity really running?

Schedule agreed with production

Methods

What is done on site, and what can be done remotely?

Audit plan

Independence

Did the auditor design or run what they are auditing?

Declaration of no conflict of interest

Confidentiality

Who receives the report, and what data may leave the site?

Engagement letter

Reporting

Report format, severity scale, response time for process owners

Engagement letter, report template

For a food site, check at scoping that the audit fits into the programme your scheme requires. For BRCGS Food Safety Issue 9, that means at least four audit dates spread throughout the year and every activity covered each year (clause 3.4.1 of the site self-assessment checklist). For IFS Food Version 8, every requirement audited within a 12-month programme carried out within 15 months at most (5.1.1, KO No. 8). The overall framework of the programme is set out in our guide to outsourced internal audits.

An example: a citrus packhouse in the Gharb plain, around Kenitra in north-western Morocco, that schedules its HACCP audit outside the packing season audits an empty hall. The audit of operations belongs in the season; the document audit of the management review can wait for the off-season.

Which documents should be sent to the auditor, and when?

Those that let the auditor target their questions, about a week before the audit, according to the lead time set at scoping. The rule is simple: send what exists, write nothing for the audit. A document produced the day before shows, and it says nothing about the real system.

Area

Useful documents

Why the auditor asks for them

All

Previous internal and external audit reports, open actions, changes since the last audit

Follow up findings and target the areas that have changed

Quality

Process map, procedures for the audited process, indicators, complaints

Compare what is prescribed, what is measured and what is done

Environment

Environmental aspects and impacts analysis, register of legal requirements, waste records

Check compliance and operational control

Health and safety

Risk assessment, accident investigations, minutes of the safety and hygiene committee

Link the declared risks to the shop floor

Food safety

HACCP plan, prerequisite programmes, verification results, food defence and food fraud plans, sanitary authorisation or approval from ONSSA, the national food safety office

Prepare floor tests and traceability

Customers

Specifications, customer audit reports

Add their requirements to the criteria

Also prepare access to the day’s records: control sheets, CCP records, work permits, cleaning logs. That is where the auditor samples. Reports and the status of actions can be shared in a single document space; at ACG, that is the Inspirra client space.

How should interviews and the floor walk be organised?

By putting the auditor in front of the real work and the people who do it. The audit plan, circulated in advance, gives the times, the places and the people to be met; the site makes sure they are available.

The opening meeting. Short: objective, scope, schedule, safety and hygiene rules, contacts, time of the closing meeting. Management or the programme manager attends.

Interviews. Plan for management on system management topics, each process owner on their process and, above all, operators at their workstations, night shift included if the scope warrants it. An auditor who meets only the quality manager is auditing a story, not a system. For a combined QHSE audit, add the maintenance manager, a member of the safety and hygiene committee (comité de sécurité et d’hygiène) if your headcount requires one, and the person who manages waste.

The floor walk. In production, on the lines within scope. Have protective equipment ready, the hygiene rules that apply to visitors, and a guide who opens doors without answering in place of the operators.

Tests. The auditor may ask for an exercise: tracing a batch, checking a CCP, reviewing a work permit, testing an alarm. Prepare the availability of the data, not the answer.

The remote part. ISO 19011:2026 expands remote audit methods and allows them to be combined with on-site auditing. A document review, an interview with a process owner at another site or the verification of closure evidence lend themselves to it; observing a workshop does not. Test the connection and the screen-sharing rules before the day.

The closing meeting. Findings are presented there before the auditor leaves. Under the ISO 19011:2026 principle of fair presentation, unresolved diverging opinions are to be recorded: challenge on the evidence, not on the tone.

How should findings be handled after the audit?

In three distinct stages: correct what must be corrected straight away, deal with the cause, then prove that the action worked. The schemes describe this cycle in the same terms.

  • BRCGS Food Safety Issue 9 requires results to be reported to the personnel responsible for the activity audited, actions and their timescales to be agreed and their completion verified, and a summary to be reviewed at management review meetings (3.4.3).
  • IFS Food Version 8 requires documented audits, results communicated to senior management and to the persons responsible, and compliances, deviations and non-conformities documented and communicated (5.1.3).
  • For a group certified to FSSC 22000 on a multi-site basis, version 7 adds a technical review of reports by the central function and the demonstration that corrective actions are effective (2.5.18.2).

Step

Who

Deadline

Evidence

Report received

Programme manager

As set in the engagement letter

Report circulated to process owners

Immediate correction

Process owner

From the closing meeting, for a serious finding

Dated record

Root cause analysis

Process owner, with their team

Set in the action plan

Written analysis

Corrective action

Process owner

Deadline agreed with the programme manager

Evidence of completion

Verification of completion

External auditor or programme manager

On receipt of the evidence

Documented closure

Effectiveness check

Auditor, at follow-up or at the next audit

Based on risk

No recurrence observed

Management review

Management

At the next review

Summary of results and decisions

The deadlines for closing certification non-conformities do not apply to internal audits: your procedure sets them. Align them with severity and with the schedule of your certification audits.

Which mistakes destroy the value of an outsourced audit?

Those that turn the audit into a formality. We see them in our assignments in Morocco, whatever the size of the site:

  1. Staging a showroom. Tidying the workshop the day before, filling in overdue records: the auditor mainly sees what is usually missing.
  2. Scheduling the audit when nothing is running. Line stopped, off-season, construction site shut down.
  3. Giving the audit to the person who built the process. A consultant who wrote the procedure does not audit it.
  4. Letting the auditor write the actions. The auditor loses their impartiality for the follow-up, and the process owner takes ownership of nothing.
  5. Closing on a statement. “Done” is not evidence; a dated record is.
  6. Forgetting the strengths. A report that also identifies conformity, as BRCGS requires (3.4.3), shows what to keep.
  7. Leaving the report in the quality department. If it does not reach the management review, it changes nothing.

A checklist for each audit: