Where do you start: PRPs or the hazard analysis?

With the PRPs. Prerequisite programmes set the basic hygiene conditions on which the hazard analysis reasons: a HACCP plan built on poorly cleaned premises or uncontrolled water ends up with too many CCPs. ISO 22000:2018 deals with PRPs in clause 8.2, before hazard control in clause 8.5.

The standard lets the organisation choose and justify its PRPs. The strongest basis today is the 2025 ISO 22002 series: the ISO page for ISO 22002-100:2025 presents it as supporting compliance with clause 8.2, to be read with the sector part for your activity, for example ISO 22002-1:2025 for manufacturing. It is not mandatory for ISO 22000 alone; it becomes mandatory if you move to FSSC 22000 Version 7.

For each PRP, a short sheet is enough, provided it answers these questions.

PRP sheet heading

What it must state

Example for pest control

Purpose

What the programme controls

Prevent pests from entering and settling

Hazard or requirement covered

Why it exists

Physical and microbiological contamination; customer requirement

Reference

The standard or text that frames it

Applicable ISO 22002 part, regulations, customer specification

Owner

Who runs it, who carries it out

Hygiene manager; contracted provider

Method and frequency

How, when, where

Bait station map, visit frequency, alert criteria

Record

What proves it is applied

Visit reports, readings, actions taken

Verification

How you know it works

Internal inspection, trend analysis

A PRP that cannot fill in the second row has no reason to exist, and the auditor will see it. Cross-cutting programmes, such as allergens, traceability or environmental monitoring, are covered on our food safety programmes page.

What are the steps, from the team to the hazard control plan?

Nine steps, which follow the Codex HACCP method and add the decisions specific to ISO 22000. The seven principles and twelve steps of the Codex are explained on our HACCP plan and ONSSA approval page; ONSSA, the Office national de sécurité sanitaire des produits alimentaires, is Morocco’s national food safety office, which approves food establishments. This table focuses on what ISO 22000 expects on top of the Codex.

Step

ISO 22000:2018 clause

What you produce

What ISO 22000 adds to the Codex

1. Appoint the food safety team

5.3 and 7.2

Membership, team leader, evidence of competence

A team leader appointed by top management, proven competence

2. Describe raw materials, finished products and intended use

8.5.1.2 to 8.5.1.4

Raw material and product sheets, uses, consumers

Food-contact materials are described too

3. Establish and confirm the flow diagrams

8.5.1.5

Diagrams verified on site, dated

A description of the processes and of their environment

4. Identify hazards and their acceptable level

8.5.2.2

Hazards listed by step, acceptable level in the finished product

The acceptable level is set and justified

5. Assess each hazard

8.5.2.3

Significant hazards retained, written method

The assessment method is described

6. Select and categorise the control measures

8.5.2.4

Each measure classified as a CCP or an OPRP, written reasoning

The OPRP category, absent from the Codex

7. Validate the measures

8.5.3

Validation file for each CCP and each OPRP

Validation comes before implementation

8. Write the hazard control plan

8.5.4

Critical limits, action criteria, monitoring, actions

CCPs and OPRPs in a single plan

9. Verify and update

8.6 and 8.8

Verification programme, analysis of results, updates

PRPs and plan updated together

Two steps are often rushed. Step 4 first: setting the acceptable level of the hazard in the finished product means reading the regulations of the countries of sale and your customers’ requirements, and it is that level that tells you whether a measure is sufficient. For an exporter, that can mean several sets of rules for the same product. Step 7 next: a measure applied before it is validated is a hypothesis put into production.

CCP or OPRP: how do you decide, measure by measure?

Through a written assessment of each measure, which takes into account, among other things, the likelihood that it fails and the severity of the consequences if it does. If the measure has a measurable critical limit and a deviation makes the product potentially unsafe, it is a CCP. If it has a measurable or observable action criterion and a deviation requires the product to be assessed, it is an OPRP.

To structure the reasoning, we ask the team five questions, measure by measure:

  • Was the measure specifically designed to reduce this hazard to an acceptable level?
  • Does another measure, downstream, catch its failure?
  • Can it be monitored fast enough to act before the product leaves?
  • Is its criterion a measurable value or an observable finding?
  • What happens to the consumer if it fails without anyone noticing?

The example below is generic: it illustrates the method for a biscuit factory, with no numerical values. Your own classifications come from your own analysis.

Control measure

Hazard targeted

Possible classification

What tips the balance

If the measure fails

Baking to a validated time and temperature combination

Pathogens brought in by eggs or flour

CCP

The only step that reduces the hazard; monitoring possible for every batch

Batches concerned isolated and assessed by a competent person

Metal detection at the end of the line

Metal fragments

CCP

Last barrier before the customer, continuous control

Product passed since the last compliant test re-run or isolated

Sieving flour before mixing

Foreign bodies, insects

OPRP

A targeted measure, but other barriers exist downstream

Sieve checked; batches sieved since the last compliant check assessed

Validated cleaning between a recipe with tree nuts and a recipe without

Undeclared allergen through cross-contact

OPRP

Observable and testable criterion, plausible failure

Product held and assessed, allergen test if needed

Label check at start-up and at each changeover

Undeclared allergen through a labelling error

OPRP

Observable criterion, plausible failure

Labels removed, product relabelled or isolated

General cleaning of the premises

Contamination of the environment

PRP

Does not target an identified significant hazard

Correction

In another biscuit factory, baking might be an OPRP if another measure, further downstream, controls the same hazard. That is precisely what the auditor checks: that the classification flows from your analysis and not from a template.

How do you validate, monitor and verify the plan?

Validate before applying, monitor during production, verify afterwards. The three activities are distinct, and confusing them is one of the most frequent causes of audit findings.

Validate (clause 8.5.3). Prove that the measure, or the combination of measures, is capable of controlling the hazard to the acceptable level. Possible evidence: published scientific data, trials on your line, regulatory requirements, sector guides, data from the equipment manufacturer. Validation is repeated after any change of recipe, equipment or process.

Monitor (clause 8.5.4.3). Measure or observe each CCP and each OPRP at a frequency that lets you trace the product concerned. A test whose result arrives after shipment is not monitoring: it is verification. The measuring equipment used is calibrated or verified (clause 8.7).

Verify (clause 8.8). Confirm that the PRPs and the plan work as intended: review of records, product testing, inspections, internal audits. Results are analysed, and the analysis feeds the update of the system (clause 8.6) and the management review.

Sites that later prepare for FSSC 22000 will find these requirements again, with additions: Version 7, for example, requires routine, risk-based site inspections to verify the PRPs (additional requirement 2.5.12 of the scheme).

Which mistakes should you avoid, and which checklist should you follow?

The ones that turn a plan that is right on paper into a plan that cannot be applied. Here are the six we find most often in the ISO 22000 plans submitted to us.

  • Copying the CCPs of a site in the same sector. Same product, different line, different barriers: the classification does not transfer.
  • Forgetting the acceptable level. Without it, you cannot say whether a measure is sufficient.
  • An OPRP without an action criterion. Nobody knows at what point to react.
  • Validation done once and for all. A new recipe or a new oven calls it into question.
  • An action that fixes the machine and forgets the product. The batch made since the last compliant measurement must be traced.
  • A plan that cannot be read at the workstation. Operators must know their limit, their criterion and what to do in case of deviation.

Before presenting the plan to an internal audit, then to the certification body, tick these points.