What makes up the budget of a BRCGS Packaging project?

Five invoiced items and one hidden one: your teams’ time. The Standard costs nothing: according to the BRCGS Guide to Certification, it can be accessed free of charge from the BRCGS online store. Everything else depends on your site.

Item

What it covers

Who invoices it

Main lever

Consultancy

Gap analysis, scope, HARA, statements of compliance, procedures, mock audit

The consultant, if you use one

Written deliverables rather than a number of days

Training

HARA team, project lead, internal auditors, operators (hygiene, process control)

Training provider or in-house training

Train in the teams’ language, once and properly

Site works and equipment

Protection of windows and lighting, washbasins, changing rooms, pest proofing, inspection equipment

Your suppliers

Decide on them after the HARA, not before

Testing

Migration tests, analyses your customers ask for, PFAS for the PPWR

Laboratories

Start from the data supplied by your ink, varnish, paper and polymer suppliers

Certification audit

Audit, report, review of corrections, travel costs

BRCGS-approved certification body

A written scope before the quote

Internal time

Project lead, HARA team, records, internal audits, meetings

You

An available project lead, with a deputy

Two rules affect the testing line. Migration tests are among the critical-use parameters to agree with the customer where relevant (clause 5.1.1). And any test critical to safety or legality must be carried out by a laboratory that is accredited or operates to the principles of ISO/IEC 17025 (5.6.6): the cheapest laboratory is not always acceptable.

Which factors make cost and timeline vary?

Scope and the intended use of the products weigh more than headcount. The table shows the factors we cost during a gap analysis.

Factor

Effect on cost

Effect on timeline

How to control it

Starting gap

A site certified to ISO 9001:2026 keeps its document foundation; a site with no system starts further back

High

Gap analysis requirement by requirement on the P701 self-assessment checklist

Number of products, materials and processes

Each family needs its description, a flow diagram verified on site and its hazard analysis

High

Group products with the same process and the same use in the HARA

Food contact

Statements of compliance, supplier information, migration tests

High, depending on how quickly suppliers respond

Ask suppliers for their declarations in the first month

Printing

Artwork management, traceability of plates and cylinders, detection of print errors during the run

Medium

Start from the existing pre-press workflow

Building and hygiene

Works decided by the HARA: protection, washbasins, segregation, proofing

Variable, depending on contractors’ lead times

Give priority to what affects hygiene-sensitive areas

Wider scope

Traded products (section 7), outsourced steps (3.8), Modules 10 and 11

Medium

Include only what your customers require

PPWR handled in parallel

Information sheets, PFAS analyses, recyclability data

Medium

Build this evidence on the BRCGS system, not alongside it

A maker of printed films in direct contact with biscuits has to deal with migration, ink set-off, validated cleaning and a statement of compliance for each reference. A carton maker supplying transport cases to citrus packhouses concentrates on foreign bodies, pallets and pests. With the same starting gap, the second project is usually shorter. Hygiene controls by material are detailed in our packaging hygiene and contamination control checklist.

How long does it take, and what stretches the timeline?

BRCGS sets no period before the audit. But the audit assesses actual implementation, through observation of practices, document review and staff interviews: a system written the month before will not pass. Several requirements assume a track record.

  • Internal audits follow a programme spread over the year, with every activity audited at least once a year (3.5.1).
  • The traceability test is run at least once a year across product groups, within 4 hours (3.10.4).
  • The recall procedure is tested at least once a year, with timings of key activities (3.14.5).
  • Flow diagrams are verified on site at least once a year (2.4.2).
  • Management review is held at least once a year (1.2.1).

What most often stretches the timeline on our assignments: ink or polymer suppliers slow to send their declarations, works started too late, a project lead with no protected time, and a HARA redone after the mock audit because it did not describe the real lines.

The only deadlines set by BRCGS come after the audit.

Official milestone

Deadline

Source

Submission of corrections, root cause analysis and preventive action plan

28 days after the audit

BRCGS Guide to Certification

Certificate issued, if certification is granted

No more than 42 calendar days after the first audit day

BRCGS Guide to Certification

New audit after an audit that did not lead to certification

No earlier than 28 calendar days after the last audit, full and announced

BRCGS079

First possible blended audit

Only at recertification, never at the initial audit

BRCGS080

How do the audit programme and the grade affect the budget?

The audit duration is calculated by the certification body with the BRCGS calculator for the Standard concerned, and it is the same for an unannounced audit as for an announced one (BRCGS079). You do not negotiate it; you bring it down by limiting the scope to what your customers need and by preparing documents so that they are found quickly.

The budget mostly slips for organisational reasons:

  • an unannounced audit that cannot go ahead because there is no production for its planned duration must be rescheduled, and the BRCGS079 protocol leaves the charging of the auditor’s time to the contract with the certification body;
  • a contract signed too late, after the four-month window has opened, moves the audit due date, may let the certificate expire and leads to a major non-conformity;
  • a refusal of access to the auditor suspends the certificate until a new unannounced audit, with a major non-conformity;
  • an audit that does not lead to certification means a new full audit, and therefore a second audit invoice.

The grade matters too: the BRCGS protocols provide for the next audit at 12 or 6 months depending on the grade, which can double the number of audits per year; the grading scale and the grades concerned are set in the Issue 7 audit protocol. That is the strongest economic argument for a serious mock audit. Preparing the audit itself is covered in our guide to BRCGS Packaging Materials Issue 7.

What can be funded, and how do you present the budget to management?

Training, in part; the rest, no. Special training contracts (contrats spéciaux de formation, CSF) are run by OFPPT, the Office de la formation professionnelle et de la promotion du travail, Morocco’s vocational training office. They cover training activities: training the HARA team, internal auditors, and operators in hygiene and process control. The certification audit and the site works are not covered, and consultancy is not covered as such. The rates and ceilings in force, the procedure and the simulation are on our CSF / OFPPT funding page: they are rules, not guaranteed amounts, and only OFPPT decides the reimbursement. These rules come from the CSF procedures manual of May 2006 and its Amendment No. 2 of 2 June 2014. Upstream, a training needs analysis linked to a certification project is eligible for support from your sector GIAC (the interprofessional groups that fund training engineering), under the GIAC procedures manual and its Amendment No. 1 of 2 June 2014.

Before you present the project to your management committee, gather these items:

The cost of a BRCGS consultant, item by item, is covered in our article on BRCGS consultancy cost in Morocco, and our case study of a flexible packaging printer shows how one project absorbs a European customer’s PPWR requests.